NEWS

Wednesday, April 9, 2025

The first transition pieces have been installed at the Baltic Power offshore wind farm

The Baltic Power project – a joint venture of ORLEN and Northland Power – has confirmed the first successful installations of the five transition pieces, that will connect foundations and offshore wind turbines at the farm. This is the first such installation on the Polish waters of the Baltic Sea.

MORE
news

Friday, November 8, 2024

A heavy-lift vessel has arrived in the Port of Gdynia, which will begin construction of the Baltic Power offshore wind farm in early 2025

A state-of-art vessel has arrived at the Port of Gdynia - the Svanen - a specialised heavy-lift vessel from Van Oord’s fleet designed for the installation of offshore wind farm foundations. This particular vessel that will start the first offshore wind farm construction in the Polish part of the Baltic Sea - Baltic Power - at the beginning of 2025.


MORE
news

Friday, October 18, 2024

First monopiles for Baltic Power offshore wind farm ready for shipment

The first shipments of foundation monopiles for the Baltic Power offshore wind farm have set off from Steelwind's factory in Nordenham. Twenty-six shipments will be made to the transhipment port, from where they will depart for the offshore construction site in early 2025.


MORE
news

Friday, October 4, 2024

Baltic Power wind farm completes first onshore connection

In the Lubiatowo area, the first of four directional drills under the coastline, beach, and seabed has been successfully completed, with no direct impact on areas of high ecological value. This phase of the project paves the way for connecting the Baltic Power offshore wind farm to its onshore substation. The 1.4 km tunnel will house power transmission cables. The drilling was conducted using HDD (horizontal directional drilling) technology.


MORE
news

Wednesday, September 25, 2024

Baltic Power introduces a temporary compensation mechanism for fishermen

Baltic Power has announced plans to implement a temporary compensation mechanism for fishermen operating in the area where the first Polish offshore wind farm is planned to be built – that includes squares in N7, N8, O7, O8 located ca. 23 km from the shore. The solution is temporary and will remain in force until the official ministerial regulation regarding the compensation system between the offshore wind sector and fishing sectors is introduced.


MORE
news

Thursday, July 25, 2024

Manufacture of key components for Baltic Power wind farm based locally in Pomerania

In preparation for the offshore installation works scheduled for the end of this year, some critical components of the Baltic Power project are currently under production. Key infrastructure, including substations for evacuating power from the offshore turbines and transmitting it to the mainland, is being constructed in the seaside region of Pomerania. Other important project components are also being manufactured in Szczecin, Kluczbork, and Żary, among other locations.


MORE
news

Thursday, June 20, 2024

POWER OF THE BALTIC - Baltic Power launches new program to support local initiatives of Łeba

An informational meeting on the "Power of the Baltic" program, initiated by Baltic Power, an investor in the project to build Poland's first offshore wind farm, is behind us. On June 19 in Łeba, representatives of non-governmental and community organizations working in the city and on behalf of local residents were able to learn about the details of the initiative.


MORE
news

Friday, May 10, 2024

Baltic Power launched informational meetings with fishermen from the Polish coast

Baltic Power has started a series of informational meetings for representatives of the fishing community in Ustka, Leba and Władysławowo about the construction of Poland's first offshore wind farm. The topics addressed were the prospects for the development of offshore wind energy in Poland, and, above all, the planned start of installation work in the Baltic Sea at the end of this year.


MORE
news

Wednesday, February 28, 2024

Summary of the program "Choczewo. Wind Powered Commune"

In early December, an exhibition summarizing the realization of initiatives under the program "Choczewo. Wind Powered Commune" was unveiled. In the libary of the Communal Cultural Center in Choczewo the results of projects that have received funding from investors involved in the polish offshore wind sector were presented.


MORE
news

Friday, February 23, 2024

Baltic Power with award for European Deal of The Year of the year 2023

Baltic Power, a joint project of the ORLEN Group and Northland Power, has been recognized and honored with the prestigious award for the best European financial transaction of the year 2023. This unique award highlights the importance of Poland's first offshore wind farm in shaping the future of renewable energy sources in the region. The award statuette was handed over to Baltic Power Managememt Board representatives Jarosław Broda and Jens Poulsen during a gala in London.


MORE