Friday, March 21, 2025

Baltic Power obtains first Design Conformity Certificates for an offshore wind farm in Poland

Baltic Power obtains first Design Conformity Certificates for an offshore wind farm in Poland
A topside of the offshore substation under construction

The Baltic Power project, a joint venture between ORLEN and Northland Power, has obtained the first Design Conformity Certificates for its turbines and offshore substations, issued by DNV. This achievement marks a significant step forward not only for the project itself but also for Poland's offshore wind industry. These certificates are crucial for the construction and subsequent operation of the offshore wind farm, ensuring compliance with applicable codes and technical standards.

Under the Act on Maritime Safety and the Act on the Promotion of Electricity Generation from Offshore Wind Farms, investors are required to present such certificates before construction begins. The objective of project certification is to limit project risks in different phases of the project. The certificates provide evidence to stakeholders that the windfarm is designed, constructed and can operate safely by fulfilling the applicable requirements. Without these approvals, the wind farm construction cannot be commenced.

Construction of an offshore wind farm is executed not only at the construction site, but also on an administrative level. Completing the design evaluation phase is not just an administrative accomplishment; it represents months of intensive engineering work. These certificates are not only an administrative success but also a historic step for offshore wind energy in Poland. We are proud to be the first offshore wind farm project in Poland to have successfully completed this process - says Jens Poulsen, Project Director and Board Member, Baltic Power.

The design conformity certificates, issued by DNV - an independent energy expert and assurance provider, authorized by the Polish Ministry of Infrastructure - are verifying that the construction designs of the wind turbines and the offshore substations are in compliance with international codes and standards and are suitable to perform under local conditions over the entire design lifetime of the offshore wind farm. They were issued prior the installation of the first monopile.

We are now looking forward to progressing through the construction phase, during which DNV will oversee the fabrication, installation and commissioning of the offshore wind farm to ensure  all activities are carried out in accordance with the requirements. The evidence of compliance will be documented in the Entry into Service Certificate which we expect in 2026 and a full Project Certificate following the completion of the offshore wind farm construction phase - adds Bennet Moeller, Engineering Design Package Manager at Baltic Power.

The Baltic Power offshore wind farm is the most advanced offshore wind project in Poland and the first one to have reached the construction phase. In 2023, the project received a final investment decision (FID) as well as financing from 25 international institutions. Both, onshore and offshore installarions are underway at the moment. Baltic Power will be among the world’s first projects to install 15 MW wind turbines and the first Polish offshore wind farm operating in the Baltic Sea, with a scheduled completion by 2026. Generating approximately 4,000 GWh of zero-emission electricity annually, Baltic Power aims to reduce CO2 emissions by around 2.8 million tons per year compared to conventional energy sources.

 

SEE ALSO

news

Monday, June 22, 2026

50 turbines installed at the Baltic Power offshore wind farm. Key testing phase soon to commence

Poland’s first offshore wind farm Baltic Power – a joint venture project of ORLEN and Northland Power – confirmed successful installation of the 50th of 76 turbines. The crucial phase of mandatory power and infrastructure tests is about to commence in the upcoming weeks. The end of installation campaign is expected in the 2nd half of 2026.


MORE
news

Monday, June 8, 2026

Baltic Power offshore wind farm signs first key contracts for the upcoming operations & maintenance phase

Once the construction phase finishes, for around 30 years, a service base in Łeba shall become an operations and maintenance center of Baltic Power offshore wind farm. The project, developed jointly by ORLEN and Northland Power, has announced the signing of the first key contracts for the operational phase with a significant participation of Polish suppliers.


MORE
news

Tuesday, March 24, 2026

Baltic Power highlights safety as core priority during Safety Day

On the 23rd of March 2026 across all offshore, onshore and office locations of the Baltic Power project, employees and contractors paused their daily activities to take part in Safety Day - a health, safety and environment (HSE) initiative aimed at strengthening awareness of the responsible safety practices that come with delivering an infrastructure project of such scale and complexity.


MORE
news

Thursday, March 19, 2026

All transition pieces connecting foundations and turbines installed at the Baltic Power offshore wind farm

Baltic Power offshore wind farm – a joint venture project of ORLEN Group and Northland Power – confirmed successful installations of all 76 transition pieces which connect foundations with wind turbines. The installation campaign of wind turbines, as well as export and inter-array cables is progressing over 23 km off the Polish coast.


MORE