Wednesday, April 9, 2025

The first transition pieces have been installed at the Baltic Power offshore wind farm

The first transition pieces have been installed at the Baltic Power offshore wind farm
First transition pieces at the Baltic Power farm installed

The Baltic Power project – a joint venture of ORLEN and Northland Power – has confirmed the first successful installations of the five transition pieces, that will connect foundations and offshore wind turbines at the farm. This is the first such installation on the Polish waters of the Baltic Sea.

Transition pieces (TPs) are the steel constructions that connect installed monopile foundations with the towers of the offshore wind turbines and offshore substations. In the Baltic Power project 78 such pieces are set to be installed. Each structure weighs up to 350 tons and measures over 20 meters. Smulders is the manufacturer of the TPs for the Baltic Power project.

Offshore construction works are intensifying at the Baltic Power wind farm. After the announcement of the first successful installation of the monopiles last month, we can confirm the first installations of the transition pieces. It is worth reminding, that the majority of secondary steel structures for the transition pieces have been manufactured at the Polish plants of Smulders in Żary, Niemodlin and Łęknica. We have the first locally produced elements of our offshore wind farm installed offshore – says Grzegorz Szabliński, CEO and The President of the Management Board, Baltic Power.

So far 5 transition pieces have been installed offshore. Van Oord – one of the most experienced global contractors in the field of offshore installations – is responsible for the transport and installation campaign. The heavy lift vessel SAL LONE, which is used for this task, measures 160 meters and has 2 cranes with 1000 tons lifting capacity each. Thanks to a dynamic positioning system  the vessel’s position is maintained no matter of conditions. The SAL LONE vessel has been on duty since 2010. SAL LONE is supported by crew transfer vessels.

Meanwhile the installations of the foundation’s monopiles are ongoing, also executed by Van Oord. All offshore installations are supervised by Baltic Power’s Marine Coordination Centre located in Baltic Power Base in Łeba. The foundation installations campaign is expected to end mid-year.

Our focus now remains firmly on the road ahead to ensure the safe and timely installation of the remaining foundations, before we commence installation of the WTGs, cables, and our offshore substations - adds Nick Ingham, Deputy EPCI Director, Baltic Power.

Several onshore construction works are underway as well. In Choczewo commune the onshore substation is being outfitted with necessary equipment, including 4 large-scale, 300 MV transformers. The service base in Łeba, that will serve the Baltic Power farm for approximately 30 years, is undergoing final equipping and preparations for daily operations. The commissioning of the Baltic Power farm is expected in 2026.

The Baltic Power offshore wind farm is the most advanced offshore wind project in Poland and the first one to have reached the construction phase. In 2023, the project received a final investment decision (FID) as well as financing from 25 international institutions. Both onshore and offshore installations are underway at the moment. Baltic Power will be among the world’s first projects to install 15 MW wind turbines and the first Polish offshore wind farm operating in the Baltic Sea. Generating approximately 4,000 GWh of zero-emission electricity annually, Baltic Power aims to reduce CO2 emissions by around 2.8 million tons per year compared to conventional energy sources.

SEE ALSO

news

Friday, July 10, 2026

Baltic Power Offshore Wind farm produces and delivers Electricity to Polish Energy Grid for the first time

A historic milestone for offshore wind energy in Poland: at the Baltic Power farm a joint venture of ORLEN and Northland Power - the first turbines have successfully passed the required tests and supplied first offshore wind power to the national energy grid. Polskie Sieci Energetyczne confirmed the receipt of energy at the onshore substation in nearby Choczewo. More than 50 out of the 76 turbines are already installed at the offshore wind farm, and the installation campaign is scheduled to be completed later this year.


MORE
news

Monday, June 22, 2026

50 turbines installed at the Baltic Power offshore wind farm. Key testing phase soon to commence

Poland’s first offshore wind farm Baltic Power – a joint venture project of ORLEN and Northland Power – confirmed successful installation of the 50th of 76 turbines. The crucial phase of mandatory power and infrastructure tests is about to commence in the upcoming weeks. The end of installation campaign is expected in the 2nd half of 2026.


MORE
news

Monday, June 8, 2026

Baltic Power offshore wind farm signs first key contracts for the upcoming operations & maintenance phase

Once the construction phase finishes, for around 30 years, a service base in Łeba shall become an operations and maintenance center of Baltic Power offshore wind farm. The project, developed jointly by ORLEN and Northland Power, has announced the signing of the first key contracts for the operational phase with a significant participation of Polish suppliers.


MORE
news

Tuesday, March 24, 2026

Baltic Power highlights safety as core priority during Safety Day

On the 23rd of March 2026 across all offshore, onshore and office locations of the Baltic Power project, employees and contractors paused their daily activities to take part in Safety Day - a health, safety and environment (HSE) initiative aimed at strengthening awareness of the responsible safety practices that come with delivering an infrastructure project of such scale and complexity.


MORE