Monday, December 9, 2024

Transition elements of the Baltic Power farm foundations from Polish factories finish production. Construction moves offshore in January 2025

Transition elements of the Baltic Power farm foundations from Polish factories finish production. Construction moves offshore in January 2025
production of secondary steel for TP's at Niemodlin, Poland

Smulders' Polish factories are in the final stages of manufacturing the key foundation elements for the Baltic Power offshore wind farm. These are the transition pieces that will connect the foundations to the wind turbines. Once assembled, they will set off for the transhipment port. Already in the first quarter of 2025, they will be installed at the first offshore wind farm in the Polish part of the Baltic Sea.

The installation of foundations consisting of monopiles and transition pieces, or so-called TP's (the distinctive yellow structures that connect the foundations and offshore wind turbines), will begin the offshore installation work of the Baltic Power farm. The installation of the monopiles will start in January, and the next phase of work will see the transitional pieces applied to the monopiles.

At the plants in Żary, Niemodlin and Łęknica, work on auxiliary structures for the transition elements, so-called secondary steel, is nearing completion. Among other things, external service platforms, external equipment structures and mooring elements for service vessels are being built there. The steel used to produce them comes from Polish steel mills.

The production of the transition pieces was a complex process, requiring advanced welding and metalworking technologies. Therefore, they were coated with special anti-corrosion coatings that will protect them for about 30 years The entire transition elements weigh more than 350 tonnes and measure 20 metres high. Work on the production of the foundations is proceeding according to schedule. Maintaining it is crucial for the project, due to the booking periods for the specialised vessels to install them and the immediately following offshore turbine installation work.

The first elements of the monopiles, manufactured by Steelwind, are already compleye and cyclically transported to the transshipment port. Van Oord, one of the world's most experienced companies in this field with a fleet of specialised installation vessels, is responsible for the installation work of the foundations at sea. A specialised floating crane, Svanen, is already stationed in the Port of Gdynia, from which the installation of 78 monopiles for turbine and offshore substation foundations will take place.

The Baltic Power offshore wind farm, a joint venture between ORLEN and Northland Power, is the most advanced offshore wind project in Poland and the only one in the construction phase. Work is progressing according to schedule, which assumes that the farm will integrate approximately 1.2 GW of power into the national energy system in 2026. At the same time, it will be one of the first farms in the world with wind turbines of 15 MW each. Baltic Power will cover approximately 3% of Poland's energy needs, thereby reducing national CO2 emissions by approximately 2.8 million tonnes per year.

SEE ALSO

news

Thursday, November 13, 2025

The first offshore wind nacelles manufactured in Poland have been installed at the Baltic Power offshore wind farm

Baltic Power project – a joint venture of ORLEN Group and Northland Power - confirmed successful installation of the first three 15 MW turbines consisting of nacelles manufactured at Vestas’ facility in Szczecin. Installation of these nacelles marks a pivotal moment for the development of local content at the emerging Polish offshore wind industry. In total, 76 turbines will be installed on the Polish waters of the Baltic Sea with several nacelles coming from the Western-Pomeranian factory.


MORE
news

Wednesday, October 29, 2025

Both offshore substations installed at Poland’s first offshore wind farm – Baltic Power

Baltic Power offshore wind farm – a joint venture project of ORLEN Group and Northland Power – completed installation of both offshore substations. These four-story structures gather energy generated by 76 wind turbines to transfer it to the onshore infrastructure. The topsides of the substations were manufactured at local shipyards in Gdańsk and Gdynia.


MORE
news

Tuesday, October 28, 2025

Baltic Power shareholder ORLEN secures PLN 3.5 billion from the National Recovery Plan for offshore wind development.

In line with its strategy, ORLEN is consistently expanding low- and zero-emission generation capacities, materially strengthening the energy security of Poland and the wider region. A key pillar of these efforts is investment in offshore wind. To advance these projects, the Group has secured PLN 3.5 billion from the National Recovery Plan (KPO) under agreements signed with Bank Gospodarstwa Krajowego (BGK).


MORE
news

Monday, July 7, 2025

BALTIC POWER CONFIRMS FIRST SUCCESSFUL INSTALLATIONS OF THE OFFSHORE WIND TURBINES FOR POLAND’S FIRST OFFSHORE WIND FARM

Baltic Power project, a joint venture between ORLEN Group and Northland Power, confirmed the first successful installation of the first 15-MW offshore wind turbine. In total 76 turbines will be installed at the Poland’s first offshore wind farm, estimated to cover 3% of national electricity demand. Commissioning is expected in 2026.


MORE