Sunday, May 21, 2023
The construction of transmission infrastructure for Baltic Power offshore wind farm is commenced
The ORLEN Group and Northland Power have commenced the construction of an onshore substation in the Choczewo municipality. The project will allow the Baltic Power wind farm to receive energy generated offshore. According to the schedule, the farm will start producing zero-carbon energy in 2026.
“As the first company in Poland, we commence constructing infrastructure allowing to deliver electricity produced offshore to the grid. We have also started work in the area of the installation terminal for offshore wind farms in Świnoujście. We are not slowing down, since making investments in modern, zero-carbon energy is a pillar of our strategy. Offshore wind farms, in addition to small nuclear reactors, will be key to transforming Poland’s electricity system and strengthening our region’s energy security. We are fully prepared to implement the project in the Baltic Sea that will provide clean, affordable energy to millions of Poles as early as 2026,” Daniel Obajtek, President of the Management Board of PKN ORLEN.

The whole accompanying infrastructure for the Baltic Power farm was designed so as to minimize the project’s environmental impact. The substation, being an onshore part of the Baltic Power wind farm, will act as a hub for cable lines transmitting electricity from offshore substations located nearly 30 kilometers away. Almost the whole route of the cable’s onshore section of approx. 7 kilometers will be routed underground. This also applies to the beach – thanks to the use of so-called directional drilling, the landfall will be routed at the depth of approx. 10 meters underground. Thanks to this, it will be invisible and will not affect the possibility to use the beach. The route of the onshore cable route has been designed so as to make the project minimally interfere with the natural environment and bypass naturally valuable areas.
“Baltic Power is an example of a project placing a special emphasis on the aspects of environmental protection, sustainable development and respect for local communities, i.e. the aspects that are so important to both Northland Power and our partner. We are all the more glad that the Baltic Power project is reaching another, such important milestone. Our farm, the construction of which will be commenced in 2024, will secure the first supplies of green energy for Poland in just a few years, as planned,” concludes Mike Crawley, President of the Management Board of Northland Power.
A consortium of GE and Enprom is responsible for the design, construction and delivery of the necessary components for the onshore substation. GE also designed the electrical system and provided high voltage power components. Enprom, a Polish company, prepared the design and is fully responsible for the construction of the substation.
Currently, Baltic Power is the most advanced offshore wind farm construction project in Poland. The company ended 2022 by fully securing the contracts for all key components necessary for the construction of the wind farm as part of the planned supply chain. In 2023, along with securing all environmental decisions and building permits, Baltic Power commences its first onshore construction works. According to the schedule, the first offshore installation works will be commenced in 2024. At the same time, in 2022 ORLEN Group made a strategic decision to build Poland’s first installation terminal for offshore wind farms. The project is being implemented in the port of Świnoujście and after being completed at the turn of 2024/2025 will be one of the most modern terminals in Europe. Its quaysides and storage yards will allow to transport and install state-of-the-art wind turbines of 15 MW and above.
The Baltic Power’s offshore wind farm will consist of 76 turbines with a unit capacity of 15 MW and a height of more than 200 meters operating in an area of approx. 130 sqm. The farm will be located approx. 23 kilometers away from the coast, at the height of Choczewo and Łeba, where the farm’s service port will be built. Once completed, the farm will be able to deliver clean energy to more than 1.5 million households.
SEE ALSO
Thursday, March 19, 2026
Baltic Power offshore wind farm – a joint venture project of ORLEN Group and Northland Power – confirmed successful installations of all 76 transition pieces which connect foundations with wind turbines. The installation campaign of wind turbines, as well as export and inter-array cables is progressing over 23 km off the Polish coast.
MORE
Monday, February 23, 2026
Located in Łeba, the Baltic Power service base has been supporting installation work in a marine area covering over 130 km² for almost a year. The first recruitment process for the operational phase of the offshore wind farm, which will supply 3% of Poland's electricity, is now underway. Among others, offshore operations coordinators and energy infrastructure operators are being sought.
MORE
Wednesday, February 18, 2026
All foundations installed at the Baltic Power offshore wind farm.
Baltic Power, a joint venture offshore wind project of ORLEN Group and Northland Power, completed the main installation works of all 78 key elements of foundations - monopiles for turbines and offshore substations. Over 20 vessels and 500 crew members and contractor representatives took part in this part of the installation campaign.
MORE
Tuesday, December 30, 2025
Baltic Power launches second round of Transitional Compensation Payments for Fishermen
Baltic Power will begin a second round of compensation payments to fishermen under its Transitional Compensation Scheme. This next stage of the program continues the support launched in 2024, when nearly 100 eligible fishing vessel owners received compensation.
MORE