Wednesday, November 30, 2022
Tender for the Baltic Power Contract Engineer Service
The Baltic Power Offshore Wind Farm (OWF) is a project under development, located in the Polish Exclusive Economic Zone in the Baltic Sea. The offshore location license covers a total area of approximately 131 km2 and the buildable area available for installation of OWF components is approximately 100 km2. Offshore export cable route is located in Polish Exclusive Economic Zone, Baltic Territorial Sea and Internal Waters. Onshore part of the project is located in Choczewo Commune, Starosty of Wejherowo. Onshore export cable lines are located within the Choczewo Forest.
The expected installed capacity of Offshore Wind Farm is up to 1200 MW, consisting of 76 wind turbine generators. The WTG and OSS substructure types are monopiles. The Inter-Array Cables (IAC) network will connect each WTG in loops to the project’s Offshore Substations (OSSs). IAC voltage level will be 66 kV. The equipment specification assumes two offshore substations (OSS) with four export cable links running from the OSS(s) to shore, connecting the OWF through the project’s Onshore Substation (ONS) to the Polish transmission system.
The purpose of the Agreement with the Engineer is to establish a comprehensive, professional and effective supervision over the execution of the design works and Construction Contracts for all tasks within Baltic Power project, ensuring proper performance of all assignments under the Contract and the achievement of the planned utility and financial effects.
The project includes 7 separate construction projects under separate building permits:
- wind turbines and foundations
- inter array cables
- offshore substations
- offshore export cables
- onshore export cables
- onshore substation
- access roads
Interested parties shall be able to demonstrate the following capabilities to be considered for invitation to bid:
In terms of technical or professional capacity Contractor shall provide and document experience:
- within the last 7 years before the lapse of the time limit for submitting requests to participate in tender procedure, and if the period of operation is shorter - within such period - in this period, it has performed jointly at least 1 service consisting in performing the function of the Contract Engineer including construction or reconstruction of HV substations 220kV and above and offshore hydrotechnical structures [preffered installation of foundation for WTG and OSS, installation of cables (IAC, EXC) installation of WTG and topside of the OSS].
- Contractor will present documents confirming that the works were performed properly, in accordance with the principles of good building practice and completed on time.
In terms of technical or professional capacity Contractor shall provide and document experience of each single person dedicated for execution of Contract:
- Resident Engineer
- Deputy Resident Engineer
- Design solution verifier
- Investor’s supervision inspector
- Construction Manager
- Work Managers
- Specialist for settlement and administration
- HSSE manager
Tender Schedule

If you have the required capabilities and want to be considered for inclusion in the Contract Engineer Service tender, please contact onshore_tender@balticpower.pl the required information by no later than 16:00 CET Friday 30th December.
Communication during tender process will be conducted only in English.
SEE ALSO
Thursday, November 13, 2025
Baltic Power project – a joint venture of ORLEN Group and Northland Power - confirmed successful installation of the first three 15 MW turbines consisting of nacelles manufactured at Vestas’ facility in Szczecin. Installation of these nacelles marks a pivotal moment for the development of local content at the emerging Polish offshore wind industry. In total, 76 turbines will be installed on the Polish waters of the Baltic Sea with several nacelles coming from the Western-Pomeranian factory.
MORE
Wednesday, October 29, 2025
Both offshore substations installed at Poland’s first offshore wind farm – Baltic Power
Baltic Power offshore wind farm – a joint venture project of ORLEN Group and Northland Power – completed installation of both offshore substations. These four-story structures gather energy generated by 76 wind turbines to transfer it to the onshore infrastructure. The topsides of the substations were manufactured at local shipyards in Gdańsk and Gdynia.
MORE
Tuesday, October 28, 2025
In line with its strategy, ORLEN is consistently expanding low- and zero-emission generation capacities, materially strengthening the energy security of Poland and the wider region. A key pillar of these efforts is investment in offshore wind. To advance these projects, the Group has secured PLN 3.5 billion from the National Recovery Plan (KPO) under agreements signed with Bank Gospodarstwa Krajowego (BGK).
MORE
Monday, July 7, 2025
Baltic Power project, a joint venture between ORLEN Group and Northland Power, confirmed the first successful installation of the first 15-MW offshore wind turbine. In total 76 turbines will be installed at the Poland’s first offshore wind farm, estimated to cover 3% of national electricity demand. Commissioning is expected in 2026.
MORE