Wednesday, November 30, 2022
Tender for the Baltic Power Contract Engineer Service

The Baltic Power Offshore Wind Farm (OWF) is a project under development, located in the Polish Exclusive Economic Zone in the Baltic Sea. The offshore location license covers a total area of approximately 131 km2 and the buildable area available for installation of OWF components is approximately 100 km2. Offshore export cable route is located in Polish Exclusive Economic Zone, Baltic Territorial Sea and Internal Waters. Onshore part of the project is located in Choczewo Commune, Starosty of Wejherowo. Onshore export cable lines are located within the Choczewo Forest.
The expected installed capacity of Offshore Wind Farm is up to 1200 MW, consisting of 76 wind turbine generators. The WTG and OSS substructure types are monopiles. The Inter-Array Cables (IAC) network will connect each WTG in loops to the project’s Offshore Substations (OSSs). IAC voltage level will be 66 kV. The equipment specification assumes two offshore substations (OSS) with four export cable links running from the OSS(s) to shore, connecting the OWF through the project’s Onshore Substation (ONS) to the Polish transmission system.
The purpose of the Agreement with the Engineer is to establish a comprehensive, professional and effective supervision over the execution of the design works and Construction Contracts for all tasks within Baltic Power project, ensuring proper performance of all assignments under the Contract and the achievement of the planned utility and financial effects.
The project includes 7 separate construction projects under separate building permits:
- wind turbines and foundations
- inter array cables
- offshore substations
- offshore export cables
- onshore export cables
- onshore substation
- access roads
Interested parties shall be able to demonstrate the following capabilities to be considered for invitation to bid:
In terms of technical or professional capacity Contractor shall provide and document experience:
- within the last 7 years before the lapse of the time limit for submitting requests to participate in tender procedure, and if the period of operation is shorter - within such period - in this period, it has performed jointly at least 1 service consisting in performing the function of the Contract Engineer including construction or reconstruction of HV substations 220kV and above and offshore hydrotechnical structures [preffered installation of foundation for WTG and OSS, installation of cables (IAC, EXC) installation of WTG and topside of the OSS].
- Contractor will present documents confirming that the works were performed properly, in accordance with the principles of good building practice and completed on time.
In terms of technical or professional capacity Contractor shall provide and document experience of each single person dedicated for execution of Contract:
- Resident Engineer
- Deputy Resident Engineer
- Design solution verifier
- Investor’s supervision inspector
- Construction Manager
- Work Managers
- Specialist for settlement and administration
- HSSE manager
Tender Schedule
If you have the required capabilities and want to be considered for inclusion in the Contract Engineer Service tender, please contact onshore_tender@balticpower.pl the required information by no later than 16:00 CET Friday 30th December.
Communication during tender process will be conducted only in English.
SEE ALSO

Friday, March 21, 2025
Baltic Power obtains first Design Conformity Certificates for an offshore wind farm in Poland
The Baltic Power project, a joint venture between ORLEN and Northland Power, has obtained the first Design Conformity Certificates for its turbines and offshore substations, issued by DNV. This achievement marks a significant step forward not only for the project itself but also for Poland's offshore wind industry. These certificates are crucial for the construction and subsequent operation of the offshore wind farm, ensuring compliance with applicable codes and technical standards.
MORE

Thursday, February 6, 2025
First foundations at the Baltic Power offshore farm installed
As scheduled, the offshore construction of the first Polish offshore wind farm Baltic Power, a joint venture between Orlen Group and Northland Power, has commenced in January. The first monopiles, the main part of the foundation, have successfully been installed in the Baltic Sea. In total, 78 foundations for both of the turbines and the offshore substations will be installed. Following the foundation work, the installation of wind turbines, substations, and subsea connecting cables will proceed. This operation is the first of its kind in Polish Baltic waters, setting the stage for a new era of energy production in the region.
MORE

Wednesday, February 5, 2025
Manufactured at shipyards in Gdynia and Gdańsk, the steel structures of two offshore substations of the Baltic Power wind farm are now completed and have sailed off to the port of Aalborg (Denmark) for the outfitting. They will be installed in the Baltic Sea this autumn.
MORE

Thursday, January 16, 2025
Changes in the Management Board of Baltic Power
Baltic Power announces that Kamil Kobyliński has been appointed to the Management Board of Baltic Power as a Member. He replaces Jarosław Broda, who has departed the project.
MORE