POWER OF THE BALTIC - Baltic Power launches new program to support local initiatives of Łeba
An informational meeting on the "Power of the Baltic" program, initiated by Baltic Power, an investor in the project to build Poland's first offshore wind farm, is behind us. On June 19 in Łeba, representatives of non-governmental and community organizations working in the city and on behalf of local residents were able to learn about the details of the initiative.
The program is an element of good neighborly activities carried out in the area where the investor is developing its activities, building a service base for offshore wind farms. It assumes financial and substantive support for initiatives submitted by residents and NGOs from Łeba. Representatives of the local community can count on financing projects that will bring social, educational, cultural and environmental benefits.

One of the goals of the initiative is to strengthen local ties, create spaces for the integration of residents and support undertakings that are important in the life of the local community. From the funds set aside for the program, grants will also be available for ecological projects aimed at protecting the environment. The results of the call for proposals in the first edition of the program will be announced in the fall of 2024. The total budget for the initiative in 2024 is PLN 150,000.00. The program is directed primarily to foundations, associations, organizational units of the Łeba Municipality and entities working for the public good.
The Baltic Power offshore wind farm is the most advanced offshore wind project in Poland. The development stage was completed in September 2023, with full financing obtained from 25 international financial institutions. Baltic Power is one of the first projects in the world to install 15 MW wind turbines and the first in the world to have a significant portion of its turbine towers made of low-carbon steel. With completion in 2026, Baltic Power will be the first Polish offshore wind farm operating in the Baltic Sea, covering 3% of the country's energy needs while reducing CO2 emissions by about 2.8 million tons per year.
SEE ALSO
Friday, July 10, 2026
A historic milestone for offshore wind energy in Poland: at the Baltic Power farm a joint venture of ORLEN and Northland Power - the first turbines have successfully passed the required tests and supplied first offshore wind power to the national energy grid. Polskie Sieci Energetyczne confirmed the receipt of energy at the onshore substation in nearby Choczewo. More than 50 out of the 76 turbines are already installed at the offshore wind farm, and the installation campaign is scheduled to be completed later this year.
MORE
Monday, June 22, 2026
50 turbines installed at the Baltic Power offshore wind farm. Key testing phase soon to commence
Poland’s first offshore wind farm Baltic Power – a joint venture project of ORLEN and Northland Power – confirmed successful installation of the 50th of 76 turbines. The crucial phase of mandatory power and infrastructure tests is about to commence in the upcoming weeks. The end of installation campaign is expected in the 2nd half of 2026.
MORE
Monday, June 8, 2026
Once the construction phase finishes, for around 30 years, a service base in Łeba shall become an operations and maintenance center of Baltic Power offshore wind farm. The project, developed jointly by ORLEN and Northland Power, has announced the signing of the first key contracts for the operational phase with a significant participation of Polish suppliers.
MORE
Tuesday, March 24, 2026
Baltic Power highlights safety as core priority during Safety Day
On the 23rd of March 2026 across all offshore, onshore and office locations of the Baltic Power project, employees and contractors paused their daily activities to take part in Safety Day - a health, safety and environment (HSE) initiative aimed at strengthening awareness of the responsible safety practices that come with delivering an infrastructure project of such scale and complexity.