Friday, November 13, 2020

PKN ORLEN: another phase of preparations for offshore wind farm project

PKN ORLEN: another phase of preparations for offshore wind farm project

The Company has commenced onshore geological surveys along the connection route for its planned offshore wind farm. The work will help delineate an underground cable route to transmit power from the offshore farm to an onshore power station. The survey will be performed in the municipality of Choczewo, where the transmission infrastructure will be built.

All the power output of the wind farm in the Baltic Sea will be transmitted underground, both along the offshore and onshore sections of the connection route. The onshore geological surveys will enable optimum delineation of the cable connection route. The first phase of the work will involve geophysical surveys performed using the electrical resistance tomography (ERT) process. Their findings will be the basis for the preliminary appraisal of the ground conditions. During the next phase, specialist equipment will be used to drill wells at up to a depth of several dozen metres, from which samples will be taken for geotechnical analysis. In parallel, geophysical surveys will be carried out in the Baltic’s shallow waters.

‘The wind farm construction in the Baltic Sea is one of key projects bringing us closer to our strategic goal of climate neutrality. Despite the epidemic crisis, we are keeping up the pace and are progressing on schedule. By 2030, we will have invested more than PLN 25bn in projects designed to mitigate our environmental impacts, opening us up to new business models. By investing in green energy, we are also building Orlen’s position as the leader of energy transition in Central Europe,’ said Daniel Obajtek, President of the PKN ORLEN Management Board.

The work on preparing the cable connection route has been contracted by PKN ORLEN to ENPROM, which is responsible for the design and building permit application for the necessary infrastructure. The contract covers the preparation of the connection route both along the offshore section: from wind farm to shore, and the onshore section: from shore to power station, from where green energy will be fed into the national power grid.

As part of the preparatory work, PKN ORLEN performed preliminary measurements of the seabed and environmental surveys of the wind farm area. On their basis, the Company has already submitted an environmental report and is currently awaiting an environmental decision for the offshore part of the project. The document will be the basis for initiating a building application procedure. Additional surveys and necessary wind measurements to be used by the wind farm’s designer are also being carried out in the Baltic. Documents prepared with the designer’s participation will include analyses of the turbine layout and assumptions related to the estimated capacity factor. They will also provide a more accurate cost estimate and timetable for the project.

PKN ORLEN is engaged in offshore wind power development through its subsidiary Baltic Power, which holds a licence to construct wind farms with an aggregate capacity of up to 1.2 GW. The licence area, of approximately 131 km2, is located about 22 km north of the Baltic coastline, near Łeba and Choczewo.

SEE ALSO

news

Friday, July 10, 2026

Baltic Power Offshore Wind farm produces and delivers Electricity to Polish Energy Grid for the first time

A historic milestone for offshore wind energy in Poland: at the Baltic Power farm a joint venture of ORLEN and Northland Power - the first turbines have successfully passed the required tests and supplied first offshore wind power to the national energy grid. Polskie Sieci Energetyczne confirmed the receipt of energy at the onshore substation in nearby Choczewo. More than 50 out of the 76 turbines are already installed at the offshore wind farm, and the installation campaign is scheduled to be completed later this year.


MORE
news

Monday, June 22, 2026

50 turbines installed at the Baltic Power offshore wind farm. Key testing phase soon to commence

Poland’s first offshore wind farm Baltic Power – a joint venture project of ORLEN and Northland Power – confirmed successful installation of the 50th of 76 turbines. The crucial phase of mandatory power and infrastructure tests is about to commence in the upcoming weeks. The end of installation campaign is expected in the 2nd half of 2026.


MORE
news

Monday, June 8, 2026

Baltic Power offshore wind farm signs first key contracts for the upcoming operations & maintenance phase

Once the construction phase finishes, for around 30 years, a service base in Łeba shall become an operations and maintenance center of Baltic Power offshore wind farm. The project, developed jointly by ORLEN and Northland Power, has announced the signing of the first key contracts for the operational phase with a significant participation of Polish suppliers.


MORE
news

Tuesday, March 24, 2026

Baltic Power highlights safety as core priority during Safety Day

On the 23rd of March 2026 across all offshore, onshore and office locations of the Baltic Power project, employees and contractors paused their daily activities to take part in Safety Day - a health, safety and environment (HSE) initiative aimed at strengthening awareness of the responsible safety practices that come with delivering an infrastructure project of such scale and complexity.


MORE