Friday, November 13, 2020

PKN ORLEN: another phase of preparations for offshore wind farm project

PKN ORLEN: another phase of preparations for offshore wind farm project

The Company has commenced onshore geological surveys along the connection route for its planned offshore wind farm. The work will help delineate an underground cable route to transmit power from the offshore farm to an onshore power station. The survey will be performed in the municipality of Choczewo, where the transmission infrastructure will be built.

All the power output of the wind farm in the Baltic Sea will be transmitted underground, both along the offshore and onshore sections of the connection route. The onshore geological surveys will enable optimum delineation of the cable connection route. The first phase of the work will involve geophysical surveys performed using the electrical resistance tomography (ERT) process. Their findings will be the basis for the preliminary appraisal of the ground conditions. During the next phase, specialist equipment will be used to drill wells at up to a depth of several dozen metres, from which samples will be taken for geotechnical analysis. In parallel, geophysical surveys will be carried out in the Baltic’s shallow waters.

‘The wind farm construction in the Baltic Sea is one of key projects bringing us closer to our strategic goal of climate neutrality. Despite the epidemic crisis, we are keeping up the pace and are progressing on schedule. By 2030, we will have invested more than PLN 25bn in projects designed to mitigate our environmental impacts, opening us up to new business models. By investing in green energy, we are also building Orlen’s position as the leader of energy transition in Central Europe,’ said Daniel Obajtek, President of the PKN ORLEN Management Board.

The work on preparing the cable connection route has been contracted by PKN ORLEN to ENPROM, which is responsible for the design and building permit application for the necessary infrastructure. The contract covers the preparation of the connection route both along the offshore section: from wind farm to shore, and the onshore section: from shore to power station, from where green energy will be fed into the national power grid.

As part of the preparatory work, PKN ORLEN performed preliminary measurements of the seabed and environmental surveys of the wind farm area. On their basis, the Company has already submitted an environmental report and is currently awaiting an environmental decision for the offshore part of the project. The document will be the basis for initiating a building application procedure. Additional surveys and necessary wind measurements to be used by the wind farm’s designer are also being carried out in the Baltic. Documents prepared with the designer’s participation will include analyses of the turbine layout and assumptions related to the estimated capacity factor. They will also provide a more accurate cost estimate and timetable for the project.

PKN ORLEN is engaged in offshore wind power development through its subsidiary Baltic Power, which holds a licence to construct wind farms with an aggregate capacity of up to 1.2 GW. The licence area, of approximately 131 km2, is located about 22 km north of the Baltic coastline, near Łeba and Choczewo.

SEE ALSO

news

Monday, July 7, 2025

BALTIC POWER CONFIRMS FIRST SUCCESSFUL INSTALLATIONS OF THE OFFSHORE WIND TURBINES FOR POLAND’S FIRST OFFSHORE WIND FARM

Baltic Power project, a joint venture between ORLEN Group and Northland Power, confirmed the first successful installation of the first 15-MW offshore wind turbine. In total 76 turbines will be installed at the Poland’s first offshore wind farm, estimated to cover 3% of national electricity demand. Commissioning is expected in 2026.


MORE
news

Tuesday, May 20, 2025

Baltic Power opens Poland’s First Offshore Wind Service Base

Baltic Power – a joint venture between ORLEN and Northland Power – has officially launched Poland’s first operations and maintenance (O&M) base dedicated to offshore wind projects. Located in Łeba, the facility will support the Baltic Power offshore wind farm for its entire lifecycle of approximately 30 years. It is already playing a key role in the ongoing offshore installation campaign.


MORE
news

Wednesday, April 9, 2025

The first transition pieces have been installed at the Baltic Power offshore wind farm

The Baltic Power project – a joint venture of ORLEN and Northland Power – has confirmed the first successful installations of the five transition pieces, that will connect foundations and offshore wind turbines at the farm. This is the first such installation on the Polish waters of the Baltic Sea.


MORE
news

Friday, March 21, 2025

Baltic Power obtains first Design Conformity Certificates for an offshore wind farm in Poland

The Baltic Power project, a joint venture between ORLEN and Northland Power, has obtained the first Design Conformity Certificates for its turbines and offshore substations, issued by DNV. This achievement marks a significant step forward not only for the project itself but also for Poland's offshore wind industry. These certificates are crucial for the construction and subsequent operation of the offshore wind farm, ensuring compliance with applicable codes and technical standards.


MORE