Friday, November 13, 2020

PKN ORLEN: another phase of preparations for offshore wind farm project

PKN ORLEN: another phase of preparations for offshore wind farm project

The Company has commenced onshore geological surveys along the connection route for its planned offshore wind farm. The work will help delineate an underground cable route to transmit power from the offshore farm to an onshore power station. The survey will be performed in the municipality of Choczewo, where the transmission infrastructure will be built.

All the power output of the wind farm in the Baltic Sea will be transmitted underground, both along the offshore and onshore sections of the connection route. The onshore geological surveys will enable optimum delineation of the cable connection route. The first phase of the work will involve geophysical surveys performed using the electrical resistance tomography (ERT) process. Their findings will be the basis for the preliminary appraisal of the ground conditions. During the next phase, specialist equipment will be used to drill wells at up to a depth of several dozen metres, from which samples will be taken for geotechnical analysis. In parallel, geophysical surveys will be carried out in the Baltic’s shallow waters.

‘The wind farm construction in the Baltic Sea is one of key projects bringing us closer to our strategic goal of climate neutrality. Despite the epidemic crisis, we are keeping up the pace and are progressing on schedule. By 2030, we will have invested more than PLN 25bn in projects designed to mitigate our environmental impacts, opening us up to new business models. By investing in green energy, we are also building Orlen’s position as the leader of energy transition in Central Europe,’ said Daniel Obajtek, President of the PKN ORLEN Management Board.

The work on preparing the cable connection route has been contracted by PKN ORLEN to ENPROM, which is responsible for the design and building permit application for the necessary infrastructure. The contract covers the preparation of the connection route both along the offshore section: from wind farm to shore, and the onshore section: from shore to power station, from where green energy will be fed into the national power grid.

As part of the preparatory work, PKN ORLEN performed preliminary measurements of the seabed and environmental surveys of the wind farm area. On their basis, the Company has already submitted an environmental report and is currently awaiting an environmental decision for the offshore part of the project. The document will be the basis for initiating a building application procedure. Additional surveys and necessary wind measurements to be used by the wind farm’s designer are also being carried out in the Baltic. Documents prepared with the designer’s participation will include analyses of the turbine layout and assumptions related to the estimated capacity factor. They will also provide a more accurate cost estimate and timetable for the project.

PKN ORLEN is engaged in offshore wind power development through its subsidiary Baltic Power, which holds a licence to construct wind farms with an aggregate capacity of up to 1.2 GW. The licence area, of approximately 131 km2, is located about 22 km north of the Baltic coastline, near Łeba and Choczewo.

SEE ALSO

news

Monday, December 9, 2024

Transition elements of the Baltic Power farm foundations from Polish factories finish production. Construction moves offshore in January 2025

Smulders' Polish factories are in the final stages of manufacturing the key foundation elements for the Baltic Power offshore wind farm. These are the transition pieces that will connect the foundations to the wind turbines. Once assembled, they will set off for the transhipment port. Already in the first quarter of 2025, they will be installed at the first offshore wind farm in the Polish part of the Baltic Sea.


MORE
news

Friday, November 15, 2024

Baltic Power launches call for applications within transitional compensation scheme for fisheries

Baltic Power, the project responsible for the construction of Poland's first offshore wind farm, has launched a call for applications for the Transitional Compensation Scheme aimed at fisheries who have carried out fishing activities in the area of the planned wind farm. This solution is transitional and will remain in force until the introduction of appropriate regulations governing the principles and scope of compensation payments between the offshore wind energy sector and the fishing industry. The annual compensation's amount will depend on the size of the vessel and vary from PLN 15,200 and PLN 48,700 each year.


MORE
news

Wednesday, November 13, 2024

Final preparations for the start of installation works of the offshore part of the Baltic Power wind farm. Polish fishermen will support construction safety at sea.

Three Polish fishing vessels will support the construction of the Baltic Power offshore wind farm. They will start operations along with the beginning of the offshore installation works scheduled for early 2025.


MORE
news

Friday, November 8, 2024

A heavy-lift vessel has arrived in the Port of Gdynia, which will begin construction of the Baltic Power offshore wind farm in early 2025

A state-of-art vessel has arrived at the Port of Gdynia - the Svanen - a specialised heavy-lift vessel from Van Oord’s fleet designed for the installation of offshore wind farm foundations. This particular vessel that will start the first offshore wind farm construction in the Polish part of the Baltic Sea - Baltic Power - at the beginning of 2025.


MORE