Environmental surveys completed by PKN ORLEN for its offshore wind farm project in Baltic Sea
After 17 months of extensive surveys by a team of over 50 experts, PKN ORLEN has finally submitted an environmental report for its offshore wind farm project to be developed in the Baltic Sea. Having completed this stage, it is now able to seek a building permit, prepare a detailed schedule and define the technical conditions for the project. The survey findings will be used to plan the project’s implementation and subsequent operation so that it optimally interacts with the environment.
As part of the work, an area of 323 km2 was surveyed using a dedicated aircraft and 18 vessels. The survey covered the geological structure of the seabed, chemical properties of the surrounding waters, as well as the flora and fauna present within the area of the proposed project. The survey report has been delivered to the Regional Directorate for Environmental Protection in Gdańsk and, after a round of consultation with stakeholders including the local community, will serve as the basis for a conditional environmental permit.
“Our offshore wind farm project is crucial not only for PKN ORLEN’s strategy to develop low- and zero-carbon generation sources, but also for Poland’s overall energy transformation. It will deliver nearly 1.2 GW of capacity installed in the Baltic Sea, which – along with our planned investments in gas assets, will result in a permanent shift in Poland’s energy mix – ensuring stable power supplies, with meaningfully reduced emissions. The completion of the survey and submission of the environmental report for our offshore project mark a milestone heralding profound changes of the entire power generation system in Poland,” said Daniel Obajtek, President of the PKN ORLEN Management Board.
The comprehensive surveys were carried out from October 2018 to February 2020. Almost 5,000 litres of sea water were sampled and examined to analyse the quality of both surface and bottom waters. As a result, their properties such as acidification levels, suspension content, aerobic conditions and the presence of harmful substances were established. Almost 400 samples of sea-floor sediments were additionally collected to obtain an insight into the content of pollutants and biogenic compounds.
As part of geophysical surveys, 72 core samples were taken at up to a depth of several metres under the seabed. Based on the data collected, it will be possible to prepare an indicative layout of the wind turbines and to provisionally define the optimum type and size of the support structures. A remotely operated submersible vehicle was used to investigate nearly 100 subsea objects, such as cable lines, rock deposit areas, prominent geological features and shipwrecks, which may affect the final layout of the turbines.
The presence of marine mammals was detected using underwater hydrophones, as well as an observation aircraft. The observations of birds and their migration lasted over 120 days at sea. Bat activity was recorded via two dedicated stations, along a section with a total length of 55 km.
The construction of an offshore wind farm is one of PKN ORLEN’s key development projects, aligned with its strategic vision to invest in low- and zero-carbon generation sources. The offshore wind power project is being run through the subsidiary Baltic Power, which holds a licence to construct wind farms with an aggregate capacity of up to 1.2 GW. The licence area, of approximately 131 km2, is located about 23 km north of the Baltic coastline, off the coast at Choczewo and Łeba. PKN ORLEN has already secured grid connection conditions and is now seeking an industry partner and technical adviser to carry out the project.
SEE ALSO
Monday, June 22, 2026
50 turbines installed at the Baltic Power offshore wind farm. Key testing phase soon to commence
Poland’s first offshore wind farm Baltic Power – a joint venture project of ORLEN and Northland Power – confirmed successful installation of the 50th of 76 turbines. The crucial phase of mandatory power and infrastructure tests is about to commence in the upcoming weeks. The end of installation campaign is expected in the 2nd half of 2026.
MORE
Monday, June 8, 2026
Once the construction phase finishes, for around 30 years, a service base in Łeba shall become an operations and maintenance center of Baltic Power offshore wind farm. The project, developed jointly by ORLEN and Northland Power, has announced the signing of the first key contracts for the operational phase with a significant participation of Polish suppliers.
MORE
Tuesday, March 24, 2026
Baltic Power highlights safety as core priority during Safety Day
On the 23rd of March 2026 across all offshore, onshore and office locations of the Baltic Power project, employees and contractors paused their daily activities to take part in Safety Day - a health, safety and environment (HSE) initiative aimed at strengthening awareness of the responsible safety practices that come with delivering an infrastructure project of such scale and complexity.
MORE
Thursday, March 19, 2026
Baltic Power offshore wind farm – a joint venture project of ORLEN Group and Northland Power – confirmed successful installations of all 76 transition pieces which connect foundations with wind turbines. The installation campaign of wind turbines, as well as export and inter-array cables is progressing over 23 km off the Polish coast.