Tuesday, December 30, 2025
Baltic Power launches second round of Transitional Compensation Payments for Fishermen
Baltic Power will begin a second round of compensation payments to fishermen under its Transitional Compensation Scheme. This next stage of the program continues the support launched in 2024, when nearly 100 eligible fishing vessel owners received compensation.
From 1 January 2026, Baltic Power—the company responsible for the construction of Poland’s first offshore wind farm—will begin accepting applications for compensation for 2026. The scheme is open to fishing vessel owners who conducted fishing activities between 2018 and 2023 in the area of the offshore wind farm under construction and its cable route (fishing squares N7, N8, O6, O7, and O8). The level of compensation will depend on the size of the vessel.
The Transitional Compensation Scheme was introduced by Baltic Power as a temporary mechanism to address restrictions on fishing activities resulting from offshore wind farm construction. It will remain in force until national regulations governing compensation for the fishing sector in the context of offshore wind development are introduced, or until construction of the wind farm is completed.
The second round of payments builds on experience gained during the first stage of the program. Fishing vessel owners who participated in the initial compensation round in 2025 will benefit from a simplified application procedure, limited to essential formalities, to ensure a smooth and timely payment process.
Applications may be submitted online or in person at information points operating during and after informational meetings organized by Baltic Power in Łeba, Ustka, and Władysławowo. The next meetings are scheduled for 12–13 January 2026.
Detailed information on eligibility criteria, required documentation, and the application process is available at www.balticpower.pl.
The Baltic Power offshore wind farm, a joint venture between ORLEN and Northland Power, is the most advanced offshore wind project in Poland and the only one that has reached the offshore construction phase. Thanks to systematic dialogue with fishing communities and the cooperation rules developed at sea, no significant incidents affecting the safety of work at sea have been reported since the start of installation work.
Baltic Power will be the first wind farm to supply Poland with energy from the sea. With a capacity of approximately 1.2 GW, the farm will be able to produce 4 TWh of energy per year, which will provide energy for over 1.5 million households. The clean energy produced by the Baltic Power offshore wind farm will be able to cover 3% of the current national demand for electricity. The construction phase is scheduled for completion in 2026.
SEE ALSO
Tuesday, November 3, 2026
Students at the Maritime School Complex in Darłowo now have a new place to gain the knowledge and skills needed to work in the offshore wind energy sector. On 23 October, the school officially opened the Interactive Educational Center. The center’s launch coincides with preparations for the commercial operation of Poland’s first offshore wind farm, Baltic Power (a joint project of ORLEN and Northland Power).
MORE
Wednesday, October 7, 2026
Baltic Power project confirmed installation of the last, 76th turbine. This milestone follows the announcement of the first power delivery to the national energy system.
MORE
Friday, July 10, 2026
A historic milestone for offshore wind energy in Poland: at the Baltic Power farm a joint venture of ORLEN and Northland Power - the first turbines have successfully passed the required tests and supplied first offshore wind power to the national energy grid. Polskie Sieci Energetyczne confirmed the receipt of energy at the onshore substation in nearby Choczewo. More than 50 out of the 76 turbines are already installed at the offshore wind farm, and the installation campaign is scheduled to be completed later this year.
MORE
Monday, June 22, 2026
50 turbines installed at the Baltic Power offshore wind farm. Key testing phase soon to commence
Poland’s first offshore wind farm Baltic Power – a joint venture project of ORLEN and Northland Power – confirmed successful installation of the 50th of 76 turbines. The crucial phase of mandatory power and infrastructure tests is about to commence in the upcoming weeks. The end of installation campaign is expected in the 2nd half of 2026.
MORE