Friday, November 15, 2024

Baltic Power launches call for applications within transitional compensation scheme for fisheries

Baltic Power launches call for applications within transitional compensation scheme for fisheries
Meeting with fishery community in Ustka, September 2024

Baltic Power, the project responsible for the construction of Poland's first offshore wind farm, has launched a call for applications for the Transitional Compensation Scheme aimed at fisheries who have carried out fishing activities in the area of the planned wind farm. This solution is transitional and will remain in force until the introduction of appropriate regulations governing the principles and scope of compensation payments between the offshore wind energy sector and the fishing industry. The annual compensation's amount will depend on the size of the vessel and vary from PLN 15,200 and PLN 48,700 each year.

The scheme was introduced to compensate local shipowners for the exclusion of areas from their fishing activities due to the ongoing construction of an offshore wind farm. The amount of support depends on the size of the fishing vessel. Owners of vessels that operated in the area of fishing squares N7, N8, O7, O8 and O6 between 2018 and 2023 can apply for compensation. At the same time, Baltic Power has provided for one-off compensation for owners of recreational fishing vessels.

- Baltic Power leads a way in the offshore wind energy sector. We were the first project to start construction of the onshore part of the investment and we are now making the final preparations to start construction of the offshore part of the farm, which is about to commence in January 2025. As a result, still waiting for the final administrative solution that will regulate the cooperation between the offshore wind and fishing sectors - we have launched our transitional compensation scheme for fisheries. At the same time, we are continuing our commitment to developing a target solution for the entire industry - says Jarosław Broda, Member of the Board of Baltic Power.

Compensation will be paid in accordance with the Transitional Scheme implemented by Baltic Power until the end of the farm construction or until final ministerial regulations are published. The call for applications will take place twice in the following periods: November 2024 - February 2025 and June - August 2025 and the compensation will cover the payment period for November-December 2024 and 2025. Applications for compensation for 2026 will be accepted similarly in the periods November 2025 - February 2026 and June - August 2026.When the ministerial regulations are introduced, the company will complete its transition programme and adapt to the new regulations.

More information and application documents can be found under the ‘FOR FISHERS’ page dedicated to the fisheries sector on www.balticpower.pl. Application documents  for payment can be downloaded from the website and submitted by email, post or courier. Applications will also be accepted at information points, which will be open after the regular information meetings held in Łeba, Ustka and Władysławowo.

- At the turn of this year, Baltic Power will become a real co-user of the Polish part of the Baltic Sea. We are aware that our activity in the Baltic Power farm construction area has an impact on the activities carried out by fishermen. For this reason we have engaged Polish fishermen and their vessels at the project preparation stage and will support them during the construction phase to ensure the safety of maritime traffic during installation works. As a responsible investor, we want to level the playing field for traditional economic sectors such as fishing - both through compensation and by involving representatives of local communities in construction works - says Jens Poulsen, Member of the Board of Baltic Power.

The Baltic Power offshore wind farm, a joint venture between ORLEN Group and Northland Power, is the most advanced offshore wind project in Poland and the only one that has reached construction phase. The preparation phase was completed in September 2023, with full financing secured from 25 international financial institutions. The construction of its onshore infrastructure has been underway since 2023, and the project will begin offshore installation work at the beginning of 2025. Baltic Power will be one of the first farms in the world to install 15 MW wind turbines. With planned completion in 2026, Baltic Power will be the first Polish offshore wind farm operating in the Baltic Sea, covering 3% of the country's energy needs (equivalent to the needs of approximately 1.5 million households), while reducing CO2 emissions by approximately 2.8 million tonnes per year.

SEE ALSO

news

Friday, July 10, 2026

Baltic Power Offshore Wind farm produces and delivers Electricity to Polish Energy Grid for the first time

A historic milestone for offshore wind energy in Poland: at the Baltic Power farm a joint venture of ORLEN and Northland Power - the first turbines have successfully passed the required tests and supplied first offshore wind power to the national energy grid. Polskie Sieci Energetyczne confirmed the receipt of energy at the onshore substation in nearby Choczewo. More than 50 out of the 76 turbines are already installed at the offshore wind farm, and the installation campaign is scheduled to be completed later this year.


MORE
news

Monday, June 22, 2026

50 turbines installed at the Baltic Power offshore wind farm. Key testing phase soon to commence

Poland’s first offshore wind farm Baltic Power – a joint venture project of ORLEN and Northland Power – confirmed successful installation of the 50th of 76 turbines. The crucial phase of mandatory power and infrastructure tests is about to commence in the upcoming weeks. The end of installation campaign is expected in the 2nd half of 2026.


MORE
news

Monday, June 8, 2026

Baltic Power offshore wind farm signs first key contracts for the upcoming operations & maintenance phase

Once the construction phase finishes, for around 30 years, a service base in Łeba shall become an operations and maintenance center of Baltic Power offshore wind farm. The project, developed jointly by ORLEN and Northland Power, has announced the signing of the first key contracts for the operational phase with a significant participation of Polish suppliers.


MORE
news

Tuesday, March 24, 2026

Baltic Power highlights safety as core priority during Safety Day

On the 23rd of March 2026 across all offshore, onshore and office locations of the Baltic Power project, employees and contractors paused their daily activities to take part in Safety Day - a health, safety and environment (HSE) initiative aimed at strengthening awareness of the responsible safety practices that come with delivering an infrastructure project of such scale and complexity.


MORE