Wednesday, June 15, 2022
Baltic Power – first project with completed geotechnical survey
For nine months, 13 specialised vessels were performing seabed tests over the wind farm site and along the power evacuation route. Based on the results, it will be possible to develop a final design of the foundations for about 70 wind turbines, offshore substations and cable connections to the onshore transmission infrastructure.
Baltic Power is the first wind farm developer on the Polish part of the Baltic Sea to have completed a geotechnical survey. The measurements were carried out over the farm’s site, with an area of more than 130 km2, and along the over 30 km long power evacuation route. A team of several hundred surveyors, technicians and operators performed thousands of measurements and soundings. The vessels involved in the campaign worked for more than 20 thousand hours, during which several thousand metres of specialist boreholes were drilled at planned locations of the foundations of various infrastructure components. Depending on the location, the drillings were made up to a target depth of several dozen metres.
“Our commitment to the development of zero carbon power generation sources, including offshore wind farms, is a strategic direction supporting the energy transition of the ORLEN Group and Poland’s economy. We are the first company operating in Poland to have completed a survey that is of key importance to the successful delivery of projects such as Baltic Power. Thus, we have confirmed that Baltic Power is one of the fastest paced projects in the Polish part of the Baltic Sea. The completion of the wind farm project, scheduled for 2026, will strengthen Poland’s energy security by delivering up to 1.2 GW of clean energy,” said Daniel Obajtek, President of the PKN ORLEN Management Board.
The obtained survey documentation is a key element to inform the final design of the farm (currently being developed), including the deployment of wind turbines, substations and cables. Since December 2021, JBO (Jörss - Blunck - Ordemann GmbH), engaged by Baltic Power, has been working on the design of the wind turbine foundations. JBO is one of the most experienced providers of structural planning services for offshore wind farm projects. Its portfolio includes dozens of foundation laying designs for wind farm projects completed since 2008, located in offshore areas of ten countries. The data from the geotechnical survey and previous work will help the contractor prepare the final design and also select the technology for mounting in place the farm components. The design work is being performed in parallel with a tender procedure for the foundation supplier, which the Company intends to close by the end of 2022.
“The intensive work and transfer of knowledge between PKN ORLEN and Northland Power have allowed us to maintain a fast pace of preparations for the Baltic Power project. The completion of the geotechnical survey is the project’s milestone, marking in practice the start of the permitting process,” said Jarosław Broda, Member of the Baltic Power Management Board.
Baltic Power is a joint project of the ORLEN Group and Northland Power. Thanks to the effective transfer of knowledge and hard work involving almost 90 experts, Baltic Power has become one of the fastest paced projects on the Baltic Sea. The construction of a wind farm with a capacity of up to 1.2 GW is scheduled for 2024–2026. During that time, about 70 wind turbines with a minimum capacity of 14 MW will be erected in the sea, ultimately supplying clean energy even to one million households.
SEE ALSO
Monday, June 22, 2026
50 turbines installed at the Baltic Power offshore wind farm. Key testing phase soon to commence
Poland’s first offshore wind farm Baltic Power – a joint venture project of ORLEN and Northland Power – confirmed successful installation of the 50th of 76 turbines. The crucial phase of mandatory power and infrastructure tests is about to commence in the upcoming weeks. The end of installation campaign is expected in the 2nd half of 2026.
MORE
Monday, June 8, 2026
Once the construction phase finishes, for around 30 years, a service base in Łeba shall become an operations and maintenance center of Baltic Power offshore wind farm. The project, developed jointly by ORLEN and Northland Power, has announced the signing of the first key contracts for the operational phase with a significant participation of Polish suppliers.
MORE
Tuesday, March 24, 2026
Baltic Power highlights safety as core priority during Safety Day
On the 23rd of March 2026 across all offshore, onshore and office locations of the Baltic Power project, employees and contractors paused their daily activities to take part in Safety Day - a health, safety and environment (HSE) initiative aimed at strengthening awareness of the responsible safety practices that come with delivering an infrastructure project of such scale and complexity.
MORE
Thursday, March 19, 2026
Baltic Power offshore wind farm – a joint venture project of ORLEN Group and Northland Power – confirmed successful installations of all 76 transition pieces which connect foundations with wind turbines. The installation campaign of wind turbines, as well as export and inter-array cables is progressing over 23 km off the Polish coast.
MORE