Monday, July 5, 2021

Baltic Power finalises geotechnical surveys of the Baltic Sea bed

Baltic Power finalises geotechnical surveys of the Baltic Sea bed

Twelve specialised vessels are beginning the main phase of geotechnical surveys of the Baltic Sea bottom in the area of the planned wind farm and along the connection route. Completion of the tests is scheduled for later this year. The results will provide a basis for the development of a detailed plan of locations of the foundations for the turbines and offshore substations and their connection to the onshore transmission infrastructure.

Baltic Power - a joint venture project between PKN ORLEN and Northland Power - is finalizing the key stage of investment preparations. The geotechnical tests will take from about 12 to about 16 weeks, depending on weather conditions. In this period, a total of 12 specialised vessels will set sail from a number of ports, to operate both in the area of the offshore wind farm and along the route of the offshore part of the power connection. The farm area, spanning more than 130 sq. km, will be the place of operation of vessels drilling boreholes and sounding to depths of up to several dozen metres. Work of a similar scope, adjusted to the nature of the project, will be carried out along the more than 30 km long route of the cable connection to be used to export power to the onshore substation.

On the basis of the data collected during the drilling and sounding, and its subsequent analysis, designers will prepare documents such as the final plan showing location of the wind turbines, their support structures, and the farm site and power export cables route. The farm seabed tests are being performed for Baltic Power by the British company Gardline Limited, while a Polish company MEWO is responsible for the measurements along the offshore connection route.

Construction of an offshore wind farm is a complex project, which requires multi-step control of the preparation processes and verification of the design assumptions. One of the key tools to avoid risks is the project certification procedure. The Company entrusted this task to an experienced Norwegian company, DNV, which is involved in this type of services in about 80% of all offshore wind farm projects worldwide. Under the contract signed with Baltic Power, DNV will carry out the certification of the final offshore wind farm project in accordance with the international IECRE standards.

The geotechnical tests on the farm site and along the cable connection route have been preceded by the start of UXO detection surveys, performed to search for any unexploded ordnance at sea. During the preliminary geophysical surveys carried out in 2019 for the purposes of an environmental report, dozens of objects that may pose a threat in the offshore construction phase were detected on the farm site. They included fragments of shipwrecks, rock formations, and remnants from World War II, such as a torpedo and probably a sea mine. A more extensive UXO survey will make it possible to verify the data already acquired and possibly identify other elements that may pose a risk on the offshore construction site.

​The construction of an offshore wind farm in the Baltic Sea is one of PKN ORLEN’s key development projects, in line with the ORLEN Group’s strategy to invest in low- and zero-carbon energy sources. The Group is working on the development of offshore wind power through its subsidiary Baltic Power, which holds a licence to construct wind farms with a total capacity of up to 1.2 GW. in partnership with Canada’s Northland Power, which has acquired a 49% stake in the project.

SEE ALSO

news

Thursday, November 13, 2025

The first offshore wind nacelles manufactured in Poland have been installed at the Baltic Power offshore wind farm

Baltic Power project – a joint venture of ORLEN Group and Northland Power - confirmed successful installation of the first three 15 MW turbines consisting of nacelles manufactured at Vestas’ facility in Szczecin. Installation of these nacelles marks a pivotal moment for the development of local content at the emerging Polish offshore wind industry. In total, 76 turbines will be installed on the Polish waters of the Baltic Sea with several nacelles coming from the Western-Pomeranian factory.


MORE
news

Wednesday, October 29, 2025

Both offshore substations installed at Poland’s first offshore wind farm – Baltic Power

Baltic Power offshore wind farm – a joint venture project of ORLEN Group and Northland Power – completed installation of both offshore substations. These four-story structures gather energy generated by 76 wind turbines to transfer it to the onshore infrastructure. The topsides of the substations were manufactured at local shipyards in Gdańsk and Gdynia.


MORE
news

Tuesday, October 28, 2025

Baltic Power shareholder ORLEN secures PLN 3.5 billion from the National Recovery Plan for offshore wind development.

In line with its strategy, ORLEN is consistently expanding low- and zero-emission generation capacities, materially strengthening the energy security of Poland and the wider region. A key pillar of these efforts is investment in offshore wind. To advance these projects, the Group has secured PLN 3.5 billion from the National Recovery Plan (KPO) under agreements signed with Bank Gospodarstwa Krajowego (BGK).


MORE
news

Monday, July 7, 2025

BALTIC POWER CONFIRMS FIRST SUCCESSFUL INSTALLATIONS OF THE OFFSHORE WIND TURBINES FOR POLAND’S FIRST OFFSHORE WIND FARM

Baltic Power project, a joint venture between ORLEN Group and Northland Power, confirmed the first successful installation of the first 15-MW offshore wind turbine. In total 76 turbines will be installed at the Poland’s first offshore wind farm, estimated to cover 3% of national electricity demand. Commissioning is expected in 2026.


MORE