Friday, March 21, 2025

Baltic Power obtains first Design Conformity Certificates for an offshore wind farm in Poland

Baltic Power obtains first Design Conformity Certificates for an offshore wind farm in Poland
A topside of the offshore substation under construction

The Baltic Power project, a joint venture between ORLEN and Northland Power, has obtained the first Design Conformity Certificates for its turbines and offshore substations, issued by DNV. This achievement marks a significant step forward not only for the project itself but also for Poland's offshore wind industry. These certificates are crucial for the construction and subsequent operation of the offshore wind farm, ensuring compliance with applicable codes and technical standards.

Under the Act on Maritime Safety and the Act on the Promotion of Electricity Generation from Offshore Wind Farms, investors are required to present such certificates before construction begins. The objective of project certification is to limit project risks in different phases of the project. The certificates provide evidence to stakeholders that the windfarm is designed, constructed and can operate safely by fulfilling the applicable requirements. Without these approvals, the wind farm construction cannot be commenced.

Construction of an offshore wind farm is executed not only at the construction site, but also on an administrative level. Completing the design evaluation phase is not just an administrative accomplishment; it represents months of intensive engineering work. These certificates are not only an administrative success but also a historic step for offshore wind energy in Poland. We are proud to be the first offshore wind farm project in Poland to have successfully completed this process - says Jens Poulsen, Project Director and Board Member, Baltic Power.

The design conformity certificates, issued by DNV - an independent energy expert and assurance provider, authorized by the Polish Ministry of Infrastructure - are verifying that the construction designs of the wind turbines and the offshore substations are in compliance with international codes and standards and are suitable to perform under local conditions over the entire design lifetime of the offshore wind farm. They were issued prior the installation of the first monopile.

We are now looking forward to progressing through the construction phase, during which DNV will oversee the fabrication, installation and commissioning of the offshore wind farm to ensure  all activities are carried out in accordance with the requirements. The evidence of compliance will be documented in the Entry into Service Certificate which we expect in 2026 and a full Project Certificate following the completion of the offshore wind farm construction phase - adds Bennet Moeller, Engineering Design Package Manager at Baltic Power.

The Baltic Power offshore wind farm is the most advanced offshore wind project in Poland and the first one to have reached the construction phase. In 2023, the project received a final investment decision (FID) as well as financing from 25 international institutions. Both, onshore and offshore installarions are underway at the moment. Baltic Power will be among the world’s first projects to install 15 MW wind turbines and the first Polish offshore wind farm operating in the Baltic Sea, with a scheduled completion by 2026. Generating approximately 4,000 GWh of zero-emission electricity annually, Baltic Power aims to reduce CO2 emissions by around 2.8 million tons per year compared to conventional energy sources.

 

SEE ALSO

news

Monday, February 23, 2026

Baltic Power is preparing for 30 years of operational phase. Recruitment for the operational phase of Poland's first offshore wind farm is underway.

Located in Łeba, the Baltic Power service base has been supporting installation work in a marine area covering over 130 km² for almost a year. The first recruitment process for the operational phase of the offshore wind farm, which will supply 3% of Poland's electricity, is now underway. Among others, offshore operations coordinators and energy infrastructure operators are being sought.


MORE
news

Wednesday, February 18, 2026

All foundations installed at the Baltic Power offshore wind farm.

Baltic Power, a joint venture offshore wind project of ORLEN Group and Northland Power, completed the main installation works of all 78 key elements of foundations - monopiles for turbines and offshore substations. Over 20 vessels and 500 crew members and contractor representatives took part in this part of the installation campaign.


MORE
news

Tuesday, December 30, 2025

Baltic Power launches second round of Transitional Compensation Payments for Fishermen

Baltic Power will begin a second round of compensation payments to fishermen under its Transitional Compensation Scheme. This next stage of the program continues the support launched in 2024, when nearly 100 eligible fishing vessel owners received compensation.


MORE
news

Thursday, November 13, 2025

The first offshore wind nacelles manufactured in Poland have been installed at the Baltic Power offshore wind farm

Baltic Power project – a joint venture of ORLEN Group and Northland Power - confirmed successful installation of the first three 15 MW turbines consisting of nacelles manufactured at Vestas’ facility in Szczecin. Installation of these nacelles marks a pivotal moment for the development of local content at the emerging Polish offshore wind industry. In total, 76 turbines will be installed on the Polish waters of the Baltic Sea with several nacelles coming from the Western-Pomeranian factory.


MORE